Control in complex systems in uncertainty conditions is one of the significant challenges for project managers. Therefore, in this paper an integrated approach based on Earned value management and risk analysis methods proposed to decrease deviations in time and cost estimation at complete. Using the proposed performance indexes based on risk scores obtained by non-parametric resampling technique, namely bootstrap, calculating more accurate estimations of final cost and duration at lower a...